Advice
G98 and G99 DNO applications
G98 and G99 are the Energy Networks Association engineering recommendations that govern connecting generation to the distribution network. The dividing line is capacity. Where total generation capacity is 16A or less per phase at low voltage — approximately 3.68kW on a single-phase 230V supply, or 11.04kW across three phases at 400V — G98 applies, the Distribution Network Operator does not have to be contacted in advance, and the installer submits an Installation Commissioning Confirmation within 28 days of commissioning. Above that threshold, a G99 application must be made and approved before installation goes ahead.
Why the network cares
The distribution network was designed to move electricity in one direction: from substations to houses. Embedded generation reverses that flow on a local circuit, and enough of it in one street changes voltage and loading conditions for everyone connected to that transformer.
G98 and G99 exist so the DNO knows what is connected, where, and at what capacity. Under G98 the volume is small enough that notification after the fact is acceptable. Under G99 the DNO wants to assess the effect on the local network before it happens, and may impose conditions or require network reinforcement.
The G98 route
This covers most domestic single-phase installations.
The sequence is simple: design, install, commission, then notify. The installer submits the Installation Commissioning Confirmation within 28 days of commissioning, recording what has been connected and where. There is no waiting period and no approval to obtain first, which is why a straightforward domestic array can be surveyed and installed within a normal lead time.
It is a notification, not a formality to be skipped. An unnotified installation is a compliance failure, it complicates any future work on the property, and it can surface awkwardly during a sale.
The G99 route
Above the threshold, the process runs the other way round.
The installer prepares an application with the proposed capacity, inverter details and protection settings, and submits it to the DNO. The DNO assesses the local network and responds — with an approval, an approval subject to conditions, or an offer that involves connection charges for network reinforcement.
Only once that approval is in place can the installation be booked. Timescales vary by DNO and by how loaded the local network is. In a constrained area an application can come back with an export limit rather than an unrestricted approval, or with a cost attached.
None of that is a reason to avoid a larger system. It is a reason to start the application early and to build the wait into your expectations rather than discovering it after signing.
Export limitation
Where the network cannot accept the full output of a system, an export limitation scheme is often the answer. The inverter and its control system are configured to restrict how much can flow out to the grid, while the system remains free to supply the house at full output.
For a household with high self-consumption — storage, an EV, a heat pump — an export-limited system can behave very much like an unrestricted one in day-to-day use. It is worth understanding the distinction before assuming a constrained network rules out the design you wanted.
Where storage complicates things
A battery that can discharge to the grid is generation capacity from the network’s point of view. So a house with an existing G98-notified array can move above the threshold simply by adding storage, and that pushes the whole installation into G99 territory.
Two consequences follow. First, a battery retrofit is not always the quick job it appears. Second, if you know storage is on the horizon, it is far better to establish the network position at the design stage of the original array than to discover it two years later.
Three-phase supplies
Three-phase is comparatively rare domestically but common on larger properties, barn conversions and anything with a workshop. The G98 threshold across three phases at 400V is approximately 11.04kW, which allows a considerably larger array before G99 applies. Where a property already has three-phase, or where an upgrade is being considered for other reasons, it changes the design options meaningfully.
What we do
We establish the supply type and existing generation at survey, size the design with the threshold in mind, and tell you plainly which route your system falls under and what that means for timescales. For G98 work we submit the commissioning confirmation within the 28-day window and put a copy in your handover pack. For G99 work we make and manage the application, and we do not book installation until approval is in hand.
For the wider picture, see solar panels explained, battery storage explained and what we install in Reading.
Common questions
What is the actual threshold?
G98 applies where total generation capacity is 16A or less per phase at low voltage. That is approximately 3.68kW on a single-phase 230V supply, or 11.04kW across three phases at 400V. Above it, G99 applies.
Can I be installed while a G99 application is pending?
No. A G99 application must be made and approved before installation. That is the substantive difference between the two routes and the reason larger systems need longer lead times.
Who submits the paperwork?
The installer. Under G98 we submit the Installation Commissioning Confirmation to the DNO within 28 days of commissioning. Under G99 we make the application and manage it through to approval before any work is booked in.
Does a battery count towards the threshold?
Storage that can export is generation capacity as far as the network is concerned, so it forms part of the assessment. This is why adding a battery to an existing array sometimes triggers a G99 application even though no panels are being added.
Sources
- Distributed Generation Connection Guide: G98 for Single Premises — Energy Networks Association. Accessed 2026-08-23.
Information reviewed on 2026-08-23.
Related services
- Solar panel installationSurvey, design, roof works, electrical works and commissioning for a domestic solar PV system.
- Battery storage installationHome battery systems sized against your consumption, sited properly and commissioned with the tariff in mind.
- Solar and battery systemsPanels, hybrid inverter and storage designed as one system, on one scaffold, with one commissioning.
- Commercial solarRooftop and ground arrays for businesses, designed around the site load profile and the grid connection available.
The technology behind it
- InvertersWhat the inverter does, how MPPT works, and how the four architectures compare honestly against each other.
- Hybrid invertersA single unit managing array, battery and house demand, and when fitting one is worth the extra cost.
- String invertersThe conventional central inverter: how strings are designed, where it is the best value, and where it is the wrong choice.
Property and roof guides
See it on a real installation
Further reading
- How many solar panels do I need?Why panel count is set by your electricity consumption and the usable area of your roof, not by the size of your house.
- Adding a battery to existing solarAC coupling versus replacing the inverter, what a retrofit survey checks, and the network paperwork it can trigger.
- What is MCS certification?What the MCS scheme covers, why it applies to both products and installers, and what it means for your paperwork.
Where we work
Book a free design and quotation
Tell us about the property and we will arrange a survey, then issue a written design and fixed quotation before any work is agreed.
